Cleanroom flooring must suit the process, cleaning chemicals, traffic, slab condition and agreed acceptance tests. Epoxy alone does not make a room sterile or compliant. Send WIRTHFLOOR your room schedule, drawings, cleaning details and shutdown window to discuss concrete preparation and resin-flooring scope with your responsible project team.

Discuss your cleanroom floorCall 0431 808 876

Start with the epoxy flooring service and concrete preparation scope. The facility owner, cleanroom designer and relevant quality or regulatory specialists should set and accept the final requirements.

Which cleanroom requirements apply to your process?

ISO 14644-1 classifies air cleanliness by airborne-particle concentration. Its scope does not by itself characterise the viable, chemical or radiological nature of particles, and it does not declare a particular flooring product suitable for every controlled environment.

Surface requirements are also process-specific. ISO 14644-9 provides a procedure for assessing particle cleanliness on solid surfaces, including floors, but does not set the cleanliness or material suitability required for a particular product or process. Those limits belong in the facility brief and validation strategy.

For Australian therapeutic-goods manufacturing, the TGA’s current PIC/S Guide to GMP PE009-17 guidance explains the applicable GMP framework and the updated Annex 1 pathway for sterile medicinal products. Other sectors—including electronics, research, healthcare, food and medical-device work—can have different standards, contracts and authority requirements. Do not copy a pharmaceutical specification into another facility without checking the actual process.

What belongs in the room-by-room flooring brief?

Prepare a room-by-room schedule covering:

  • the product, process and consequence of contamination;
  • the nominated room classification or grade and operating state;
  • particle, microbial, chemical or electrostatic controls relevant to the process;
  • cleaners, disinfectants, concentrations, temperatures, contact times and frequency;
  • foot, trolley, pallet, equipment, impact and point loads;
  • wet or dry operation, drains, falls, bunds and spill response;
  • coving, wall junctions, plinths, penetrations, doorways and transitions;
  • shutdown, ventilation, odour and adjacent-operation constraints; and
  • the tests, records and people authorised to accept the finished work.

“Easy to clean”, “chemical resistant”, “low VOC”, “antimicrobial”, “conductive” and “non-slip” are not complete requirements. Each needs a test method, condition, limit and evidence for the proposed system.

How should you compare complete flooring systems?

Epoxy, polyurethane, resin-mortar, methyl methacrylate and other systems are not interchangeable. A build-up may include concrete preparation, repairs, primer, body layers, coving, texture and a topcoat. Performance depends on the exact products, thickness, interfaces, substrate, installation conditions and exposure.

A resin system can reduce joints across an area, but it still has terminations, movement joints, drains, penetrations and repair points. “Seamless” must not be used to imply sterile, maintenance-free, unable to shed particles or immune to cracking and delamination.

For chemical exposure, list the actual agents and obtain current written resistance data for their concentrations, temperatures and contact times. A result for intermittent splash does not establish suitability for prolonged ponding, immersion or repeated hot cleaning. The Wirth Floor chemical-resistant flooring guide provides a detailed exposure checklist.

What needs checking in the slab and floor junctions?

Inspect cracks, movement and construction joints, spalls, laitance, previous coatings, adhesive, contamination, damp areas, repairs, flatness, falls and access. A coating is not a structural repair, waterproofing design or substitute for resolving active water entry. Moisture tests and acceptance limits must follow the selected complete system and project requirements rather than one generic percentage.

Agree how coving, drains, plinths, service penetrations, door thresholds and movement joints will be built and inspected. Eliminating an intended movement joint can transfer movement into the coating. Poor falls or drain details can leave ponding that changes cleaning, slip and chemical exposure.

What evidence should you request before approval?

01 / REQUIREMENTS

Define the exposure

Record the process, cleaning chemicals, traffic, details and acceptance limits.

02 / SYSTEM

Match the evidence

Check current data for the exact build-up and conditions, then agree the sample and inspection plan.

03 / HANDOVER

Keep the records

Agree tests, deviations, cleaning instructions and who accepts the installed work.

Before approval, request the current technical and safety data for the complete system and record:

  • substrate, preparation, profile and moisture criteria;
  • layer sequence, thickness, reinforcement and compatible details;
  • application temperature, humidity, ventilation and recoat windows;
  • chemical, cleaning, wear, impact and temperature evidence for the stated exposure;
  • any required particle, outgassing, electrostatic, fire, slip or other project tests;
  • colour, gloss, texture and acceptable visual variation;
  • repairability, cleaning, inspection and maintenance requirements; and
  • sample area, witness points and final acceptance method.

A manufacturer statement can support a specified property, but it does not replace the facility’s risk assessment, design, qualification or validation. Evidence should match the exact products and installed build, not a resin family name.

How should installation and reopening be planned?

Plan isolation, access, material movement, temporary barriers, dust or slurry, waste, ventilation, odour, ignition risks and protection of adjacent operations. Concrete grinding can generate respirable crystalline silica. Workplace Health and Safety Queensland’s floor-grinder guidance describes engineering-control options and links the applicable Queensland silica requirements.

Return-to-service periods are product- and condition-specific. Distinguish walk-on access, equipment reinstatement, cleaning, chemical exposure and full operation. A surface that feels hard is not necessarily ready for decontamination chemicals, wheeled loads or validation work.

What should the handover and maintenance records cover?

Agree who will inspect preparation, layers, details, repairs and the completed surface. Handover should include product and batch records, application conditions, test results, photographs, deviations, repair maps, cleaning instructions and maintenance triggers. The facility’s responsible team then determines whether the room and process meet their qualification or validation requirements.

Continue to inspect joints, coving, drains, impact zones, wear paths, staining, pinholes, cracks and local loss of adhesion. Changes to disinfectants, equipment, traffic or operating temperature should trigger a compatibility review rather than an assumption that the original system remains suitable.

What should you send for a flooring discussion?

Wirth Floor can discuss concrete preparation and resin-flooring scope for Brisbane and South East Queensland projects. Send the room schedule, drawings, existing slab information, cleaning and chemical exposures, required evidence, shutdown constraints and responsible design contacts through the project enquiry page.

Cleanroom flooring questions

Does epoxy flooring make a cleanroom sterile?

No. Flooring is one part of the controlled environment. A resin name or seamless appearance does not establish sterility, classification or compliance. The facility team must specify the complete system and assess it within the process, contamination controls and acceptance plan.

What cleaning information should go in the flooring brief?

List every cleaner and disinfectant, concentration, temperature, contact time and frequency. Include splash, ponding or immersion conditions. Request current written compatibility evidence for the proposed complete system rather than assuming all epoxy finishes resist the same chemicals.

Can an existing slab be coated without preparation?

The slab needs assessment for previous coatings, contamination, cracks, moisture, joints, falls and access. Preparation and repair requirements follow the selected system and substrate condition. A coating does not resolve structural movement or active water entry.

When can a cleanroom return to use after flooring work?

Agree separate conditions for walk-on access, equipment reinstatement, washing, chemical exposure and full operation. These depend on the products, installation conditions and facility plan. The responsible team must also allow for required inspection, qualification or validation before reopening.

What should I send WIRTHFLOOR for a scope discussion?

Send the suburb, room schedule, drawings or area, existing slab photographs, cleaning and chemical details, required performance evidence and shutdown window. Include the responsible project contacts. Further information or an inspection may be needed before scope, cost and timing can be confirmed.

Discuss preparation and flooring scope

Send WIRTHFLOOR your room brief and slab photographs or call 0431 808 876. Review epoxy flooring and the floor preparation quote checklist before comparing scopes.